Highrise Glass Facade Repair

  • Project Title Line 1: Highrise
  • Project Title Line 2: Glass Facade Repair
  • Project Summary: Installed a 250kg double-glazed unit near tramlines using an internal crane, tenants had access.
  • Client: Knight Frank
  • Time & Team: 1 day, 5 people
  • Video Link: https://youtu.be/jc_b2Aizk2U?si=RJ_Y-7Hw6FJoGAGi

Client

Time & Team

The Ask:

Double glazing a premier building close to tramlines in a prominent area.

The Challenge:

Prominent, high foot traffic location, close to tram lines. This project took meticulous planning by our project managers.

Result:

Using an internal floor crane and motorised lifting equipment, a double-glazed 250kg unit, sourced from a local supplier was put into place while tenants still had access to the building. On a job like this, our project management included safety consultation to help Knight Frank get the job done.

Read more …Highrise Glass Facade Repair